case study: control room relocation
New control room operational within 24 hours Challenge A control room in the south east of England had to be relocated to a new, bespoke designed installation in the Midlands – quickly and safely, with less than one day's interruption to operations. The entire existing control room was then dis-assembled and key systems were relocated and re-assembled in the new, explosion proof structure at the new location. All work was carried out under special site safety requirements and in a tight window of time during a low power requirement generation period. The move was completed and the new control room operational in one day. London